Runway to stay shut from 10am to 6pm for over 4 months, 60-70% of flights may operate during night hours; work expected to ...
Chaudhary Charan Singh International Airport will recarpet its runway from March 1 to July 15. No flights will operate ...
The project is expected to have minimal impact on daily flight operations, with the number of flights handled reducing ...
The Lucknow airport is gearing up for a crucial runway recarpeting project, set to take place from March 1 to July 15. While ...
The recarpeting will impact daily flight operations slightly, reducing the number of flights handled from 140 to 132 per day.
There will be no flights to take off or land at Lucknow airport from 10 am to 6 pm from the 1st of March. The Airport will ...
Lucknow Airport will undergo runway recarpeting from March 1 to July 15, impacting flight operations. The project aims to ...
With the runway at Chaudhary Charan Singh International (CCSI) Airport in Lucknow set to undergo recarpeting, flight services ...
Flight operations at Lucknow’s Chaudhary Charan Singh International (CCSI) Airport will remain restricted for eight hours ...
Due to the recarpeting of Chaudhary Charan Singh International Airport's runway from March 1 to July 15, flights will be ...
Lucknow Airport to begin Runway 09/27 recarpeting from March 1, 2025, with completion expected by July 15. The project aims ...